Crescent Construction Update
CRESCENT - Bhikhachak, By-Pass road, Anishabad, Patna
Tower C Raft Work Construction Update January 2022
Crescent Block A Construction update January 2022
Block B Construction Update January 2022
Block-C, Earth Excavation Started on Date: 03-12-2021
Tower A October construction update 2021, 7th floor casting and 4th floor Brick work
Tower B Construction Update October 2021 Brick work of 11th floor and and Plaster of 10th floor
Block B August 2021 Month construction update
Block A August 2021 Month construction update
Block B june 2021 Month construction update
Block A construction update in June 2021
Block - A in Crescent March 2021


Block - B in Crescent March 2021


Block A work progress in Jan 2021


Block -B of Crescent jan 2021


Crescent Block B October 2020


Second floor Roof Casting of Block -B of Crescent, done on 1st Oct 2020




First floor Roof Casting of Block -B of Crescent, done on 1st Oct 2020




Ground floor Roof Casting of Block - B of Crescent, Done on 1st Oct 2020




Block-A, Bar Binding and Casting Work of Raft done on 09-11-2020





Block-A, Soling and PCC work for Raft done on Date: 28-10-2020 to 01-11-2020





Block-A, Earth Excavation for Raft Work, Date: 20-10-2020



Block-B, Raft Work dated: 26-02-2020





Bhumi Pujan Date: 06-12-2019